Turning a cavern into a new metro begins with concrete
The last tunnels for the Blue Line to Barkarby are currently being blasted. Parallel to this, bare caverns are being converted into the new metro. One word covers the first step: concrete.

About 250 unique concrete structures will be built along the four-kilometre stretch from Akalla to Barkarby. These include tunnel walls, utility buildings, pump pits, station buildings, escalator shafts, ticket halls and ventilation towers above ground.
“The production principle is the same for all structures,” says Christer Vestergren, construction manager for concrete and steel structures.

The wooden formwork is built, the rebar is put in place and the concrete is poured. After three or four days, the concrete has hardened and the formwork can be removed.
“We don’t pour concrete where doors, gates or pipes are to be installed. In such places we create cavities, voids inside the formwork.”


40 concrete works under way
The rough concrete surfaces might not look that great, but they will rarely be visible in the finished metro. However, concrete provides the foundations for the escalators, ticket halls and platforms to be built later on.
While the last tunnels are being blasted for the Blue Line to Barkarby, some 40 concrete works are also under way. The next phase will then begin: kitting out the stations and tunnels with, for example, power, tracks, escalators, lifts, floors and other surfaces.
“But we won’t be finished before then. There will be some overlap in the work. That’s how the metro extension has been planned,” says Christer.
Getting all the pieces of the puzzle in place requires effective coordination, planning and logistics, which is a challenge when working in a tunnel under the ground. “In a tunnel, you always have a roof overhead. When building above ground, there’s usually a tall crane on hand to help move the heavy rebar. Getting the construction materials in place takes a lot longer in the tunnels.”
Media
Write to: Emma Sahlman
Phone: 072-582 44 30
Do you have any questions?
Write to: SL customer service
Phone: 08-600 10 00
News
News 2025-03-21Yes to platform screen doors on the Yellow Line
News 2024-10-10Localization study underway for a metro to Bromma Airport area
News 2024-01-12Here’s where even more new metro lines might be built
News 2023-10-12Stone cold blasting at Gullmarsplan
News 2023-09-27The yellow line is planned for unattended train operation
News 2023-09-14Photos: Look under ground in Hökarängen
News 2023-06-20New video explains expanded depot
News 2023-06-20See the stations of the future today
News 2023-06-20Yellow Line moving south
News 2023-06-20Looking into further expansion of the metro system
News 2023-06-19Full speed above and under ground in Nacka
News 2023-03-28Underground experiments for enhanced health and safety
News 2023-03-02Cool tunnel works - here the rock will be frozen
News 2023-01-30This is the first time that the metro is being built with a large drill
News 2022-12-19Blasting is now being performed at 61 sites simultaneously
News 2022-12-05Tunnel work exceeds climate goals
News 2022-11-17End of the line today – but maybe not tomorrow
News 2022-10-27A patchwork of tunnels
News 2022-10-20Securing lift shaft walls a challenging task
News 2022-10-13The tunnels are growing day by day – here’s everything that’s good to go
News 2022-09-07Tunnels under water – how does that work?
News 2022-08-26The heart is key
News 2022-06-29New series on what’s happening under your feet
News 2021-12-21Check on all larger rock contracts
News 2017-05-02New Metro between Fridhemsplan and Älvsjö