Blasting is now being performed at 61 sites simultaneously
A record number of tunnels are currently being drilled and blasted out. The high number is due to the several different types of tunnels that are being built, and because the tunnels are growing in a number of different directions.

Drilling and blasting work is currently being performed at a total of 61 underground fronts, in various directions. This concerns the building of track tunnels where the trains will run, but also service tunnels and connecting cross tunnels.
A front is the point at which the machines are about to penetrate the rock, in order to first seal the area around the tunnel and then drill holes for the explosives. After the blast, the front will have moved forwards a few more metres.

Where the most – and least – blasting work is taking place
One of the areas where construction is taking place on the most fronts at the same time is eastern Södermalm, where tunnels are being drilled and blasted at 8 fronts towards both the north and the south. The southbound tracks branch off towards Söderort and Nacka, which means that five tunnels are being worked on at the same time (track tunnels and a service tunnel).
In Barkarby, there are currently only three active tunnel fronts. This is because the space that has been excavated almost reaches the whole way between Akalla and Barkarby. Some blasting work remains to be done in some of the existing tunnels at Akalla station. This work will continue throughout 2023.
Number of fronts right now:
Here you can see how many tunnel fronts are being built at each location, and you can also click through to the progress map, where you can see how much has been blasted out of each section:
Blue Line to Barkarby Number of tunnel fronts: 3
Yellow Line to Arenastaden Hagastaden: 8 Södra Hagalund: 3 Arenastaden: 1 (work tunnel)
Blue Line to Nacka Sickla: 5 Järla: 5 Nacka: 6
Blue Line to Söderort Gullmarsplan: 7 Sockenplan: 3
Blue Line to Södermalm Blasieholmen: 3 Östra Södermalm: 8 Hammarby Sjöstad: 5
Expanded depot in Högdalen 4 fronts
Metro to Älvsjö Planning for the new line is underway
Media
Write to: Emma Sahlman
Phone: 072-582 44 30
Do you have any questions?
Write to: SL customer service
Phone: 08-600 10 00
News
News 2025-03-21Yes to platform screen doors on the Yellow Line
News 2024-10-10Localization study underway for a metro to Bromma Airport area
News 2024-01-12Here’s where even more new metro lines might be built
News 2023-10-12Stone cold blasting at Gullmarsplan
News 2023-09-27The yellow line is planned for unattended train operation
News 2023-09-14Photos: Look under ground in Hökarängen
News 2023-06-20New video explains expanded depot
News 2023-06-20See the stations of the future today
News 2023-06-20Yellow Line moving south
News 2023-06-20Looking into further expansion of the metro system
News 2023-06-19Full speed above and under ground in Nacka
News 2023-03-28Underground experiments for enhanced health and safety
News 2023-03-02Cool tunnel works - here the rock will be frozen
News 2023-01-30This is the first time that the metro is being built with a large drill
News 2022-12-05Tunnel work exceeds climate goals
News 2022-11-17End of the line today – but maybe not tomorrow
News 2022-10-27A patchwork of tunnels
News 2022-10-20Securing lift shaft walls a challenging task
News 2022-10-13The tunnels are growing day by day – here’s everything that’s good to go
News 2022-09-08Turning a cavern into a new metro begins with concrete
News 2022-09-07Tunnels under water – how does that work?
News 2022-08-26The heart is key
News 2022-06-29New series on what’s happening under your feet
News 2021-12-21Check on all larger rock contracts
News 2017-05-02New Metro between Fridhemsplan and Älvsjö