The yellow line is planned for unattended train operation
On Tuesday 26 September, Region Stockholm’s traffic committee decided that the metro line to Älvsjö will have unattendes train operation – for the first time in Stockholm.

Unattended train operation means, for example, that no driver’s cab is needed, but the passengers can see the tunnel during the trip. The solution already exists today in many places in the world, with Copenhagen being the closest.
– Exactly which trains we will buy in is not yet clear, but what we do know is that they will be customized according to our needs. Both in terms of number and furnishings, we are planning for the expected number of passengers by 2060. An advantage of unattended train operation is that it is easier to add more trains if necessary, says Johan Brantmark, director of the metro to Älvsjö.
Giant drill
The new yellow line between Fridhemsplan and Älvsjö will be separate from the rest of the metro system. That is why it can be built in a different way.
– The constructions that are underway now are all extensions, where we add some stations to existing lines. Then we need to build for the same type of train and the same signaling system. On the Yellow Line, we can do things differently – and then we must take advantage of the technological development that has taken place, says Johan Brantmark, director of the metro to Älvsjö.
In addition to unattended train operation, the metro to Älvsjö will be built using a different technique than the rest of the metro system – it will be bored with a large boring machine.
Smaller stations
The stations will also be smaller, with platforms 75 meters long instead of today’s 145 meters. This will allow us to run shorter trains with more frequent departures as it is more logical and causal and make the total travel time and waiting time shorter.
Right now, the planning work for the new line is underway.
Media
Write to: Emma Sahlman
Phone: 072-582 44 30
Do you have any questions?
Write to: SL customer service
Phone: 08-600 10 00
News
News 2025-03-21Yes to platform screen doors on the Yellow Line
News 2024-10-10Localization study underway for a metro to Bromma Airport area
News 2024-02-23Useful links for companies looking to establish business in Sweden
News 2024-01-12Here’s where even more new metro lines might be built
News 2023-10-12Stone cold blasting at Gullmarsplan
News 2023-09-14Photos: Look under ground in Hökarängen
News 2023-06-20New video explains expanded depot
News 2023-06-20See the stations of the future today
News 2023-06-20Yellow Line moving south
News 2023-06-20Looking into further expansion of the metro system
News 2023-06-19Full speed above and under ground in Nacka
News 2023-03-28Underground experiments for enhanced health and safety
News 2023-03-02Cool tunnel works - here the rock will be frozen
News 2023-01-30This is the first time that the metro is being built with a large drill
News 2022-12-19Blasting is now being performed at 61 sites simultaneously
News 2022-12-05Tunnel work exceeds climate goals
News 2022-11-17End of the line today – but maybe not tomorrow
News 2022-10-27A patchwork of tunnels
News 2022-10-20Securing lift shaft walls a challenging task
News 2022-10-13The tunnels are growing day by day – here’s everything that’s good to go
News 2022-09-08Turning a cavern into a new metro begins with concrete
News 2022-09-07Tunnels under water – how does that work?
News 2022-08-26The heart is key
News 2022-06-29New series on what’s happening under your feet
News 2021-12-21Check on all larger rock contracts
News 2017-05-02New Metro between Fridhemsplan and Älvsjö