New station in Hagalund

A decision proposal from the county council’s senior management team has now been tabled. Decisions by the County Council Assembly and the County Council Executive Board are expected during the spring.
The plan is for the new metro station to be located between the already approved stations at Arenastaden and Hagastaden. The location of the station and the proposed entrances were presented during a consultation process at the beginning of the year, and everything is set for the metro station to be included in the railway plan to be submitted later in the year.
“Yes, we have been laying the groundwork for this station for a while, in order to be ready to start construction at the same time as the rest of the Yellow Line,” says Project Manager Malin Harders.
Construction of the Yellow Line is scheduled to begin in 2018 and is expected to take six years.
Media
Write to: Emma Sahlman
Phone: 072-582 44 30
Do you have any questions?
Write to: SL customer service
Phone: 08-600 10 00
News
News 2025-03-21Yes to platform screen doors on the Yellow Line
News 2024-10-10Localization study underway for a metro to Bromma Airport area
News 2024-02-23Useful links for companies looking to establish business in Sweden
News 2024-01-12Here’s where even more new metro lines might be built
News 2023-10-12Stone cold blasting at Gullmarsplan
News 2023-09-27The yellow line is planned for unattended train operation
News 2023-09-14Photos: Look under ground in Hökarängen
News 2023-06-20New video explains expanded depot
News 2023-06-20See the stations of the future today
News 2023-06-20Yellow Line moving south
News 2023-06-20Looking into further expansion of the metro system
News 2023-06-19Full speed above and under ground in Nacka
News 2023-03-28Underground experiments for enhanced health and safety
News 2023-03-02Cool tunnel works - here the rock will be frozen
News 2023-01-30This is the first time that the metro is being built with a large drill
News 2022-12-19Blasting is now being performed at 61 sites simultaneously
News 2022-12-05Tunnel work exceeds climate goals
News 2022-11-17End of the line today – but maybe not tomorrow
News 2022-10-27A patchwork of tunnels
News 2022-10-20Securing lift shaft walls a challenging task
News 2022-10-13The tunnels are growing day by day – here’s everything that’s good to go
News 2022-09-08Turning a cavern into a new metro begins with concrete
News 2022-09-07Tunnels under water – how does that work?
News 2022-08-26The heart is key
News 2022-06-29New series on what’s happening under your feet
News 2021-12-21Check on all larger rock contracts
News 2021-04-08Cooperation is key to a good work environment
News 2021-04-08Högdalen depot is the heart of the new metro
News 2021-04-08Still a popular expansion – despite construction disruptions and interruptions
News 2021-03-23See the first platform for the metro
News 2021-03-23Positive message from the government regarding rubble
News 2021-03-23Careful work under Karolinska
News 2021-01-07The mountain accommodating the new metro
News 2021-01-07Close quarter between the bypass and the new metro
News 2021-01-07How empty tunnels become a metro
News 2020-04-15A first blast in Södermalm
News 2019-12-04Results from transportation tests
News 2019-10-15Planning for the new line starts in 2020
News 2019-10-08Testing of rock transporting by boat on Blasieholmen
News 2019-09-09Tracks cut in preparation for tunnel construction
News 2019-08-28Final stage for the Yellow line
News 2019-08-27Shifting up a gear in Barkarby this autumn
News 2019-06-13"We must be hard"
News 2019-05-09“The opposite of a high-rise”
News 2019-03-18Loud start for the new Metro
News 2019-02-05Time for the first work tunnels
News 2018-11-20Great interest when the world came to Stockholm
News 2018-11-17Important milestone for Blue Line to Nacka, Södermalm and Söderort
News 2018-11-16First railway plan decided
News 2018-10-22We're ready! Do you want to join us?
News 2018-10-03New thinking behind improved Metro operations
News 2018-09-18Registration now open for this year's Supplier Day
News 2018-08-30International Award for Architecture given to the Yellow Line
News 2018-06-01Major procurements for construction of tunnels
News 2018-05-28Green light from court for Yellow line
News 2018-05-24Follow the New Metro Administration on Linkedin
News 2018-02-26Soon time for the first procurement
News 2018-02-19On the road to zero emissions
News 2017-11-28Egg shells, solar cells and availability – that is how the new metro will be sustainable
News 2017-11-06Many curious about future business opportunities
News 2017-08-29Environmental permit for the Metro’s Yellow Line to be reviewed this spring
News 2017-08-07What is a railway plan?
News 2017-07-31The Passenger in focus
News 2017-05-04Documents ready - Nacka and southbound are now applying for an environmental permit
News 2017-05-02New Metro between Fridhemsplan and Älvsjö
News 2017-03-01From planning to opening – how we’re building the Metro
News 2017-02-21One of the world’s deepest Metros
News 2017-02-15We will begin to move pipes and conduits during this year
News 2017-02-01The track tunnel for the depot will be constructed below ground
News 2016-11-28Sofia station – one of a kind
News 2016-11-07Andrapris i den stora infrastrukturtävlingen Be Inspired Awards
News 2016-10-21Tunnelbanan till Nacka nominerad till internationellt pris
News 2016-09-30Start on artwork in the new metro
News 2016-06-13Sustainability is a natural aspect of constructing the new metro
News 2016-04-11Newsletter for contractors
News 2016-03-22Be part of the expansion of Stockholm’s metro!
- News 2016-03-11
The new Metro is environmentally certified
News 2016-03-11New depot to be at Högdalen
News 2016-03-11Which artist is to decorate which station has now been revealed
- News 2016-03-11
All the views expressed at the autumn consultation are now compiled