“The opposite of a high-rise”

Published 2019-05-06
When the Blue Line is extended from Kungsträdgården, the first stop will be Sofia in East Södermalm. The tunnels will go through rock, on a straight course under Saltsjön.
That is one of the explanations why the station will be so deep – 100 metres below the surface.
“Under Saltsjön there is a weakness zone in the rock that we need to go beneath. Södermalm is also at a high level, so overall it will be this deep,” says Andreas Burghauser, project director for the Blue Line to Södermalm.
The station itself, with the platforms underground and the ticket hall in Stigbergsparken 100 metres above, will be built both from below and from above.
“We will build a very large shaft and then fill it with content. You could compare it with building a high-rise, but downwards instead of upwards,” says Andreas Burghauser.
The deepest station in the world today is 105.5 metres below the ground, in Ukraine’s capital Kiev. But Region Stockholm has no ambition to beat the record.
“We are building as deep as we need to and we have a responsibility to look after the taxpayers’ money. Building the deepest in the world is not a goal for us,” says Andreas Burghauser.
New conditions and requirements
The last major expansion of the Metro took place around 40 years ago, when the Blue Line was built. Now another annual ring is being added to Stockholm’s Metro network and this time there are new rules, requirements and construction methods.
What is new at Sofia Stations is that passengers can take lifts instead of escalators up to street level.
“As a passenger, it is hard to tell if the platform you are standing on is 10 or 100 metres below the surface, but taking the lift up will certainly be a novelty for many. There will be eight lifts with space for 30 people in each. There is nothing like that on the Metro today,” says Andreas Burghauser.
Going up in the lift will take about 30 seconds, a lot faster than it would have been with escalators and a faster trip up to ground level than at many of today’s stations.
The first part of Sofia Station to be built is a work tunnel from ground level at Londonviadukten, where machinery, personnel, building materials and rock spoil will be transported throughout the construction period.
If all necessary permits are in place, work will begin in autumn 2019.
Media
Write to: Emma Sahlman
Phone: 072-582 44 30
Do you have any questions?
Write to: SL customer service
Phone: 08-600 10 00
News
News 2025-03-21Yes to platform screen doors on the Yellow Line
News 2024-10-10Localization study underway for a metro to Bromma Airport area
News 2024-02-23Useful links for companies looking to establish business in Sweden
News 2024-01-12Here’s where even more new metro lines might be built
News 2023-10-12Stone cold blasting at Gullmarsplan
News 2023-09-27The yellow line is planned for unattended train operation
News 2023-09-14Photos: Look under ground in Hökarängen
News 2023-06-20New video explains expanded depot
News 2023-06-20See the stations of the future today
News 2023-06-20Yellow Line moving south
News 2023-06-20Looking into further expansion of the metro system
News 2023-06-19Full speed above and under ground in Nacka
News 2023-03-28Underground experiments for enhanced health and safety
News 2023-03-02Cool tunnel works - here the rock will be frozen
News 2023-01-30This is the first time that the metro is being built with a large drill
News 2022-12-19Blasting is now being performed at 61 sites simultaneously
News 2022-12-05Tunnel work exceeds climate goals
News 2022-11-17End of the line today – but maybe not tomorrow
News 2022-10-27A patchwork of tunnels
News 2022-10-20Securing lift shaft walls a challenging task
News 2022-10-13The tunnels are growing day by day – here’s everything that’s good to go
News 2022-09-08Turning a cavern into a new metro begins with concrete
News 2022-09-07Tunnels under water – how does that work?
News 2022-08-26The heart is key
News 2022-06-29New series on what’s happening under your feet
News 2021-12-21Check on all larger rock contracts
News 2021-04-08Cooperation is key to a good work environment
News 2021-04-08Högdalen depot is the heart of the new metro
News 2021-04-08Still a popular expansion – despite construction disruptions and interruptions
News 2021-03-23See the first platform for the metro
News 2021-03-23Positive message from the government regarding rubble
News 2021-03-23Careful work under Karolinska
News 2021-01-07The mountain accommodating the new metro
News 2021-01-07Close quarter between the bypass and the new metro
News 2021-01-07How empty tunnels become a metro
News 2020-04-15A first blast in Södermalm
News 2019-12-04Results from transportation tests
News 2019-10-15Planning for the new line starts in 2020
News 2019-10-08Testing of rock transporting by boat on Blasieholmen
News 2019-09-09Tracks cut in preparation for tunnel construction
News 2019-08-28Final stage for the Yellow line
News 2019-08-27Shifting up a gear in Barkarby this autumn
News 2019-06-13"We must be hard"
News 2019-03-18Loud start for the new Metro
News 2019-02-05Time for the first work tunnels
News 2018-11-20Great interest when the world came to Stockholm
News 2018-11-17Important milestone for Blue Line to Nacka, Södermalm and Söderort
News 2018-11-16First railway plan decided
News 2018-10-22We're ready! Do you want to join us?
News 2018-10-03New thinking behind improved Metro operations
News 2018-09-18Registration now open for this year's Supplier Day
News 2018-08-30International Award for Architecture given to the Yellow Line
News 2018-06-01Major procurements for construction of tunnels
News 2018-05-28Green light from court for Yellow line
News 2018-05-24Follow the New Metro Administration on Linkedin
News 2018-02-26Soon time for the first procurement
News 2018-02-19On the road to zero emissions
News 2017-11-28Egg shells, solar cells and availability – that is how the new metro will be sustainable
News 2017-11-06Many curious about future business opportunities
News 2017-08-29Environmental permit for the Metro’s Yellow Line to be reviewed this spring
News 2017-08-07What is a railway plan?
News 2017-07-31The Passenger in focus
News 2017-05-04Documents ready - Nacka and southbound are now applying for an environmental permit
News 2017-05-02New Metro between Fridhemsplan and Älvsjö
News 2017-03-23New station in Hagalund
News 2017-03-01From planning to opening – how we’re building the Metro
News 2017-02-21One of the world’s deepest Metros
News 2017-02-15We will begin to move pipes and conduits during this year
News 2017-02-01The track tunnel for the depot will be constructed below ground
News 2016-11-28Sofia station – one of a kind
News 2016-11-07Andrapris i den stora infrastrukturtävlingen Be Inspired Awards
News 2016-10-21Tunnelbanan till Nacka nominerad till internationellt pris
News 2016-09-30Start on artwork in the new metro
News 2016-06-13Sustainability is a natural aspect of constructing the new metro
News 2016-04-11Newsletter for contractors
News 2016-03-22Be part of the expansion of Stockholm’s metro!
- News 2016-03-11
The new Metro is environmentally certified
News 2016-03-11New depot to be at Högdalen
News 2016-03-11Which artist is to decorate which station has now been revealed
- News 2016-03-11
All the views expressed at the autumn consultation are now compiled