Photos: Look under ground in Hökarängen
A new tunnel is being built between Hökarängen and Högdalsdepån so that the depot can receive trains from both the Green Line to Farsta and to Hagsätra which in the future will be part of the Blue Line. Join us under ground to see how it goes.

At Örbyleden in Hökarängen in southern Stockholm is the the entrance that is used to bring machines and workers down into the tunnel, and take out the blasted rock. The new tunnel will be 2.5 kilometers long and is planned to be completed by the end of 2024.
Click here to read more about the project

Groundwater is a major concern when building a tunnel. To seal off water leakage, a technique called grouting is used. When grouting, long holes are first drilled diagonally outwards in the rock in front of the tunnel front. For each grouting session, about twenty holes of 24 meters long are drilled. Then cement is injected into the boreholes. The cement finds its way into cracks and cavities in the rock and prevents groundwater from leaking into the tunnel. This process can take up to ten hours.

In the yellow machine, a so-called grouting platform, the cement used in grouting is mixed. The white bags contain dry cement that will soon be mixed.

When the grouting is complete, it is time to drill holes for blasting. A computerized drilling rig drills up to 250 holes into the rock, with precise length and position settings. It usually takes between five and seven hours to drill all the holes.

Before blasting, workers load all the holes with igniters and explosives by hand. They use a lifting crane to reach the higher holes.Each blast advances the tunnel by five to ten meters.

After blasting, all the blasted rock must be unloaded. After each blasting, workers unload 1200 to 1600 tons of rock. This is a quieter job that can be done at night.

Underground, it is hard to keep track of the blasting direction. That’s why the measurement technician plays a vital role. They measure the tunnel direction and ensure that it follows the right course and shape.

Sometimes some rocks are not fully blasted away. In that case, workers mark the protruding rocks with spray paint. Then they do a small extra blasting before resuming the work as planned.

Then the tunnel needs to be secured. First, workers remove loose stones by scrapping. Then they spray concrete on the roof and walls to prevent new stones from falling down. Finally, they drill long bolts into the rock wall to stabilize it. Then they repeat the whole process from grouting.
The Högdal depot is being expanded
When the metro system in Stockholm gets longer, more trains are needed. The Högdals depot needs to be expanded to accommodate the new trains. A new track tunnel is also being built to connect the depot and the metro to Farsta, so that trains can enter and exit via both Högdalen and Hökarängen. The entire work on the expanded depot in Högdalen will be completed in 2026.
Do you have any questions?
Write to Customer service or call at 08-600 10 00
News
News 2025-03-21Yes to platform screen doors on the Yellow Line
News 2024-10-10Localization study underway for a metro to Bromma Airport area
News 2024-02-23Useful links for companies looking to establish business in Sweden
News 2024-01-12Here’s where even more new metro lines might be built
News 2023-10-12Stone cold blasting at Gullmarsplan
News 2023-09-27The yellow line is planned for unattended train operation
News 2023-06-20New video explains expanded depot
News 2023-06-20See the stations of the future today
News 2023-06-20Yellow Line moving south
News 2023-06-20Looking into further expansion of the metro system
News 2023-06-19Full speed above and under ground in Nacka
News 2023-03-28Underground experiments for enhanced health and safety
News 2023-03-02Cool tunnel works - here the rock will be frozen
News 2023-01-30This is the first time that the metro is being built with a large drill
News 2022-12-19Blasting is now being performed at 61 sites simultaneously
News 2022-12-05Tunnel work exceeds climate goals
News 2022-11-17End of the line today – but maybe not tomorrow
News 2022-10-27A patchwork of tunnels
News 2022-10-20Securing lift shaft walls a challenging task
News 2022-10-13The tunnels are growing day by day – here’s everything that’s good to go
News 2022-09-08Turning a cavern into a new metro begins with concrete
News 2022-09-07Tunnels under water – how does that work?
News 2022-08-26The heart is key
News 2022-06-29New series on what’s happening under your feet
News 2021-12-21Check on all larger rock contracts
News 2017-05-02New Metro between Fridhemsplan and Älvsjö